This section is to provide updates and information on current and past projects that the Cache Highline Water Association is part of.
Logan & Northern Canal Piping and Pressurization Project
Cache Water Restoration Project
This section is to provide updates and information on current and past projects that the Cache Highline Water Association is part of.
Logan & Northern Canal Piping and Pressurization Project
Cache Water Restoration Project
October 3 Flow Testing
7/12/13 Construction Update
6/21/13 Construction Update
6/14/13 Construction Update
6/7/13 Construction Update
5/31/13 Construction Update
5/24/13 Construction Update
5/17/13 Construction Update
5/10/13 Construction Update
5/2/13 Construction Update
4/26/13 Construction Update
4/19/13 Construction Update
4/12/13 Construction Update
4/6/13 Construction Update
3/29/13 Construction Update
3/22/13 Construction Update
3/15/13 Construction Update
3/9/13 Construction Update
3/2/13 Construction Update
2/22/13 Construction Update
2/15/13 Construction Update
2/8/13 Construction Update
2/2/13 Construction Update
1/26/13 Construction Update
1/18/13 Construction Update
1/11/13 Construction Update
1/5/13 Construction Update
12/29/12 Construction Update
12/22/12 Construction Update
12/15/12 Construction Update
12/8/12 Construction Update
11/30/12 Construction Update
11/21/12 Construction Update
11/16/12 Design Update
11/15/12 Construction Update
11/9/12 Construction Update
11/1/12 Construction Update
10/30/12 1500 North Construction Update
10/26/12 Construction Update
10/19/12 Construction Update
10/13/12 Construction Update
10/6/12 Construction Update
9/27/12 Construction Update
9/14/12 Construction Update
9/1/12 Construction Update
8/18/12 Construction Update
Week Ending March 1, 2014
Week Ending Feb. 22, 2014
Week Ending Feb. 15, 2014
Week Ending Feb. 8, 2014
Week Ending Feb. 1, 2014
Week Ending Jan. 25, 2014
Week Ending Jan. 18, 2014
Week Ending Jan. 11, 2014
Week Ending Jan. 4, 2014
Week Ending Dec. 28, 2013
Week Ending Dec. 21, 2013
Week Ending Dec. 14, 2013
Week Ending Dec. 7, 2013
Week Ending Nov. 30, 2013
Week Ending Nov. 23, 2013
Week Ending Nov. 16, 2013
Week Ending Nov. 9, 2013
Week Ending Nov. 2, 2013
Week Ending Oct. 26, 2013
Week Ending Oct. 19, 2013
Week Ending Oct. 12, 2013
Week Ending Oct. 5, 2013
Week Ending Sept. 28, 2013
Week Ending Sept. 21, 2013
Week Ending Sept. 14, 2013
Week Ending Sept. 7, 2013
Week Ending Aug. 31, 2013
Week Ending Aug. 24, 2013
Week Ending Aug. 17, 2013
Week Ending Aug. 10, 2013
Week Ending Aug. 3, 2013
Week Ending July 27, 2013
Week Ending July 20, 2013
Week Ending July 13, 2013
Week Ending July 6, 2013
Week Ending June 29, 2013
Week Ending June 22, 2013
Week Ending June 15, 2013
Week Ending June 8, 2013
Week Ending June 1, 2013
Week Ending May 25, 2013
Week Ending May 18, 2013
Week Ending May 11, 2013
Week Ending May 4, 2013
Week Ending April 27, 2013
Week Ending April 20, 2013
Week Ending April 13, 2013
Week Ending April 6, 2013
Week Ending March 30, 2013
Week Ending March 23, 2013
Week Ending March 16, 2013
Week Ending March 9, 2013
Week Ending March 2, 2013
Week Ending Feb. 23, 2013
Week Ending Feb. 16, 2013
Week Ending Feb. 9, 2013
Week Ending Feb. 2, 2013
Week Ending Jan. 26, 2013
Week Ending Jan. 19, 2013
Week Ending Jan. 12, 2013
Week Ending Jan. 5, 2013
Week Ending Dec. 29, 2012
Week Ending Dec. 22, 2012
Week Ending Dec. 15, 2012
Week Ending Dec. 8, 2012
Week Ending Dec. 1, 2012
Week Ending Nov. 24, 2012
Week Ending Nov. 17, 2012
Week Ending Nov. 10, 2012
Week Ending Nov. 3, 2012
Week Ending Oct. 27, 2012
Week Ending Oct. 20, 2012
Week Ending Oct. 13, 2012
Week Ending Oct. 6, 2012
Week Ending Sept. 29, 2012
Week Ending Sept. 22, 2012
Week Ending Sept. 15, 2012
Feb. 2014 - LHPS Shareholder Update
Feb. 2014 - CWRP Financial Update
May 2013 CWRP "Media Day" Video
3/4/13 Project Update - Logan & Northern Canal Co. Stockholder Meeting
CWRP Video Overview
CWRP Fact Sheet
September 2012 Newsletter
Tree/Vegetation Removal/Trimming Area Exhibit (East Bench Corridor)
Tree/Vegetation Removal/Trimming Area Exhibit (600 E. - 800 E. Corridor)
Bonneville Shoreline Trail Closure
CWRP Landscape Restoration Guidelines
August 2012 - 1500 North Construction Update
Spring 2012 Newsletter
The Cache Water Restoration Project (CWRP) was initiated in the aftermath of the July 2009 landslide on the hillside below 400 North in Logan which breached a section of the Logan and Northern Canal. Due to public safety concerns associated with the unstable hillside, a section of canal was closed indefinitely, preventing water distribution to shareholders. The CWRP seeks to manage the design and construction of measures to restore water to shareholders and provide safe and reliable water delivery solutions.
In the aftermath of the 2009 landslide on the hillside below 400 North, federal funds were procured and an Environmental Impact Statement (EIS) for water restoration was completed and approved in 2011. The EIS included an open public process and was conducted in accordance with National Environmental Policy Act (NEPA) requirements. The study established a purpose and need statement for water restoration, identified a preferred alternative and evaluated potential impacts and mitigation measures for the natural and human environment.
Click here to view the Final EIS.
Click here to view the EIS Preferred Alternative.
Since the canal breach in 2009, shareholders of the Logan and Northern Canal, including farmers and homeowners, have had limited or no access to water. In many cases, this has significantly impacted the livelihoods of stakeholders who rely on the water for agricultural and other purposes. The urgency of restoring water delivery is especially felt by these individuals and affects the community as a whole both economically and culturally. Proposed measures are aimed at restoring service in the most timely, safe and efficient manner.
The EIS proposed modifications to the Logan and Northern as well as the Logan, Smithfield, Hyde Park Canals.The canals are located in an unincorporated area of Cache County and the communities of Logan, North Logan, Hyde Park and Smithfield. Click here to view a map of the project area.
Click here to view a map of proposed water restoration measures outlined in the EIS. Proposed measures are conceptual and subject to refinement during the final design process within the project purpose and need outlined in the EIS.
Enclosure of the existing canal in box culvert and pipe will restore safe and reliable service to water users. Public safety will be significantly improved in unstable areas where open canal is now exposed. Additionally, canal capacity will be more efficient as less water will be lost to seepage and canal maintenance needs will be reduced.
The EIS included a rigorous evaluation of project purpose and need and possible alternatives to address the need. Through this process, it was determined that public safety is the overriding impetus for proposed water restoration measures. Considering the known instability of the hillside below 400 North and history of landslides in the area, reconstruction of the canal through the breached area in an open or piped conveyance system would pose significant risks to public safety and liability issues for the canal companies. Cost to permanently repair the hillside also presents risks given the many geotechnical unknowns. Restoration measures proposed in the EIS protect public safety while improving water delivery methods to shareholders in the process.
Project design is expected to be completed by spring 2013. Construction began in late summer 2012, with total project completion expected by spring 2014. Construction will be adapted to preserve canal flow during the principal irrigation season.
Cache County hired a program management team to determine project goals, coordinate with stakeholders, complete preliminary geotechnical surveys and conceptual design, recommend the most efficient method of project delivery and develop procurement packages for potential designers and contractors to bid on the project.
The process of hiring a project designer and contractor was competitive, with equal opportunity for all qualified consultants, vendors and contractors. The process followed state procurement guidelines and the eventual selection was based on both cost and qualifications.
The project is being designed and constructed according to a contracting method called Construction Management General Contractor (CM/GC) which utilizes an integrated "Team" approach applying modern management techniques to the planning, design, and construction of a project in order to control time and cost, and to assure quality for the project owner. The CM/GC method includes both pre-construction and construction phase services. The CWRP CM/GC Team includes the owner (Cache County, NRCS), program manager (J-U-B Engineers, Inc.), design engineer (Montgomery Watson & Harza) and contractor (Whitaker Construction Co.), who are all working in tandem to deliver a quality project.
Following is the tentative construction schedule:
Irrigation flows for most shareholders concluded on Oct. 1, 2012 and are expected to resume in late spring 2013. Shareholders along Canyon Road are expected to have access to irrigation water through Oct. 31, 2012.
Federal funding procured through the Natural Resource Conservations Service’s (NRCS) Emergency Watershed Protection Program is expected to fund 75% of the project. Local entities including the Logan and Northern Irrigation Company, Logan Hyde Park Smithfield Canal Company, Logan City, North Logan City, Hyde Park, Smithfield and Cache County will share costs of the remaining 25%.
The cities of Logan, North Logan, Hyde Park and Smithfield all utilize the canal system to convey storm water. The project will restore conveyance capacity that has been lost since the canal breach and will allow further conveyance options in the future. Since municipalities will benefit, each is contributing to the local cost share.
Federal sources will fund 75% of project costs. The remaining amount will be funded by the irrigation company shareholders, municipalities and Cache County.
(Oct. 2012)
Most construction activities will be confined to canal property and existing easements. The project team is evaluating possible impacts to existing landscaping within canal right-of-way, easements and adjacent private property. Compensation or in-kind replacements will be provided to property owners for landscaping impacts on private property. Foliage and other vertical obstructions on the edge of the canal within the easement will be removed for installation of the irrigation pipeline and a gravel maintenance access road. The project team will coordinate with property owners prior to any removals. Following construction, disturbed areas will then be largely vegetated with native grasses except in areas where adjacent property owners wish to place turf grass, sod or other flat improvements that will not inhibit the access, operation and maintenance of the canal. For more detailed information on project landscape restoration guidelines, click here.
Irrigation canals have served farmers and other irrigators in Cache Valley for over 100 years. The legal right to the use of the underlying land for ownership and canal operation has been acquired by prescriptive use under Utah law, and entails the inherent legal right to use the adjoining land as is necessary to maintain, repair and replace the canals. The prescriptive easement varies in width along the canal corridor but has a maximum width of approximately 20’ from the toe of the slope on either side of the canal embankment.
Under Utah law, the owner of a canal has a clear and affirmative duty to maintain the canal so as to prevent waste of water, to prevent injury, and to prevent damage to the property of others. Through the CWRP, access is being restored to maintain, repair and replace the canals. The gravel access road will be approximately 9’-12’ wide and run parallel to the canal within the existing easement. Following construction, it will largely be vegetated with native grasses. The canal company or others as outlined in agreements will be responsible for maintenance of the access road.
Pipeline installation is being done by an experienced contractor with third party oversight per current construction standards and requirements. The pipeline is adequately designed to hold the operating pressures. It is made of PVC material that has been tested and is regularly used for pressure pipe applications. Insurance requirements must be determined by individual homeowners’ policy providers.
The existing open canal channel will remain open to collect and convey spring and storm water run-off. The CWRP will not provide any improvements to the existing channel to collect spring water. Any improvements after the project is complete would be performed by Logan City.
As outlined in the EIS, the existing open canal system through the golf course will be modified. To address aesthetic and course functionality concerns, the project team is working with the golf course to identify possible mitigation measures. Construction activities will also be phased to minimize impacts to golf course operations.
The facility’s power generation capacity will be reduced with project implementation as flows from the Logan River that have historically entered the Logan and Northern Canal below the facility will be diverted above the power plant. There is an existing agreement between the irrigation company and Logan City addressing the impacts.
Public involvement will continue to be an important component of the project as it progresses. Cache County has employed a project-dedicated public involvement team to coordinate stakeholder concerns and keep the public informed throughout project design and implementation.
07/08/2016 Construction Update
06/08/2016 Construction Update
06/03/2016 Construction Update
05/26/2016 Construction Update
05/18/2016 Construction Update
05/12/2016 Construction Update
05/04/2016 Construction Update
04/27/2016 Construction Update
04/20/2016 Construction Update
04/18/2016 Construction Update
04/08/2016 Construction Update
03/31/2016 Construction Update
03/24/2016 Construction Update
03/17/2016 Construction Update
03/10/2016 Construction Update
03/04/2016 Construction Update
02/26/2016 Construction Update
02/22/2016 Construction Update
02/19/2016 Construction Update
02/16/2016 Construction Update
02/05/2016 Construction Update
01/22/2016 Construction Update
01/14/2016 Construction Update
01/07/2016 Construction Update
12/18/2015 Construction Update
12/03/2015 Construction Update
11/19/2015 Construction Update
11/06/2015 Construction Update
11/02/2015 Construction Update
10/23/2015 Construction Update
10/09/2015 Construction Update
Draft Environmental Assessment
LNCPPP Fact Sheet - April 215 (Introduction, Features, Benefits, Schedule, Funding, Shareholder Involvement)
Project limits include the area within the Logan and Northern Canal prescriptive easement between 1500 North in North Logan and 4400 North, just north of Hyde Park. Click here to view a map of the project area (Click here for a lower resolution Map).
An Environmental Assessment (EA) is underway for the project. A 30-day public comment period is part of the process.
Project design will be completed from fall 2014 through spring 2015, with construction planned for fall 2015 through spring 2016.
To facilitate construction, irrigation flows may be terminated by Oct. 1, 2015 and are expected to resume in late spring 2016 in time for the irrigation season.
The project is funded through a loan from the Division of Water Resources and a $1 million grant from the Bureau of Reclamation.
Shareholders will be responsible for loan repayment to the Division of Water Resources.
The project consists primarily of solid wall fused High Density Polyethylene Pipe (HDPE) buried in the west bank of the canal. Metered turnouts will provide pressurized irrigation to shareholders.
Most construction activities will be confined to existing canal easements. The project team is evaluating possible impacts to existing landscaping within canal right-of-way, easements and adjacent private property. Compensation or in-kind replacements will be provided to property owners for landscaping impacts on private property. Foliage and other vertical obstructions on the edge of the canal within the easement will be removed for installation of the irrigation pipeline. The project team will coordinate with property owners prior to any removals. Following construction, disturbed areas will then be largely re-vegetated with native grasses except in areas where adjacent property owners wish to place turf grass, sod or other flat improvements that will not inhibit the access, operation and maintenance of the canal. For more detailed information on project landscape restoration guidelines, check back on this website for further information. Typical Section Trimming Section
Irrigation canals have served farmers and other irrigators in Cache Valley for over 100 years. The legal right to own and use the underlying land for canal operations has been acquired by prescriptive use under Utah law, and entails the inherent legal right to use the adjoining land as is necessary to maintain, repair and replace the canals. The prescriptive easement width varies along the canal corridor. The width of the easement is sufficient to operate and maintain the facilities with standard equipment. Please refer to the Canal Easement Legal Summary.
Pipeline installation will be completed by an experienced contractor with third party oversight per current construction standards and requirements. The pipeline will be adequately designed to hold operating pressures. It will consist of HDPE material that has been tested and is regularly used for pressurized pipe applications. Insurance requirements must be determined by individual homeowners’ policy providers.
No trail additions or improvements are planned with the project. Local municipalities may consider trails in the future as separate projects.
Yes, the existing channel will remain intact for storm water conveyance, but may be modified in some areas.
The project will provide shareholder turnouts at existing turnouts, or combined turnouts where feasible with a shutoff valve, meter and connection to existing lateral piping. It is the responsibility of lateral owners to ensure water delivery with the increased pressure provided by the project.
An alternative turnout for gravity flow can be installed if approved by Cache Highline Water Association (CHWA).
The project team is respectful of private property rights and intends to coordinate individually with each affected landowner who will be impacted outside the easement to minimize potential property impacts. Consistent with state law, existing property owners retain land ownership while the canal company maintains a prescriptive easement within the canal corridor. The easement provides the impetus for the canal operators to safely and efficiently deliver water to shareholders, including improvements to the system. The LNCPPP project team desires to work in partnership with landowners to complete the improvements.
CHWA, Cache County and the Cities of North Logan and Hyde Park will be responsible for the maintenance and care of the storm water channel.
The environmental study process includes a 30-day formal public comment period. Additionally, the CHWA has employed a project-dedicated public involvement team to coordinate concerns and keep the public informed throughout project duration. Stakeholders with questions or concerns may contact Andy Neff by calling 435-770-4114 or emailing This email address is being protected from spambots. You need JavaScript enabled to view it.. Regular updates and notice of the public comment period will be posted to the CHWA website: Cachehighline.com.
To see what is planned for your individual turnout, click on the overview map, find your location on the map and click there. The link will take you to an aerial overview of your property and turnout location.
Existing turnouts will be typically replaced with a pressurized turnout as shown in the Pressure Turnout illustration. Where circumstances allow, turnouts in close proximity may be combined and a pipe with lateral valves will be installed as shown in the Pressure Turnout with Multiple Users illustration.
Where existing gravity ditches are used, an energy dissipation box may be installed on the turnout to allow the water to be used to serve the shareholder. Special approval from the board will be necessary for this type of turnout to be installed.
The channel will not be piped with this project. The municipalities will determine if the open channel will be improved or piped for storm water purposes. Any improvements to the channel will be at the municipality’s expense.
CHWA is coordinating with the cities to drain storm water and spring water from the open channel at conducive locations to prevent stagnant water..
In July 2009, a landslide occurred along a hillside adjacent to Canyon Road in the City of Logan in Cache County, Utah. As a result of the landslide, a section of the Logan and Northern canal, a locally managed irrigation canal, broke away. This landslide caused a breach of the canal, preventing water distribution and requiring the indefinite closure of a section of the canal. This closure affects other parts of the local irrigation water delivery system, resulting in the canal not delivering all water allocated to local water shareholders.
A Final Environmental Impact Statement (EIS) for the restoration of water service to shareholders of the Logan and Northern Irrigation Company was completed in 2011. Several agencies participated and are working closely to create a framework by which water delivery solutions can be implemented. The Cache Water Restoration Project seeks to manage the design and construction of measures to restore water to shareholders and provide safe and reliable water delivery solutions.
Click here to view a map showing the EIS Preferred Alternative.
The project team will use this website and other methods to keep you informed as this project progresses.